Aminex has provided its clearest operational roadmap yet for the next stage of the Ntorya development, with the joint venture approving work programmes covering the remainder of 2026 and 2027 and projecting gross expenditure of up to $75 million.
The update confirms that first gas remains targeted for December, initially through NT-2, while the newly prioritised Ntorya-Central location will now formally become Ntorya-3, or NT-3, when drilling begins. More significantly for the longer-term development, the programme also introduces two further potential appraisal/development wells, Ntorya-East and Ntorya-West, which could be drilled back-to-back after NT-3 and any required NT-1 workover.
The announcement therefore provides much more than another timetable update. It begins to show how Ntorya could move rapidly from first production into a continuing drilling and development campaign extending through 2027.
Aminex's wholly owned Tanzanian subsidiary Ndovu Resources and operator ARA Petroleum Tanzania recently met to consider both the revised 2026 work programme and budget and the provisional programme for 2027.
Both have now been approved by the joint venture.
Together they envisage gross expenditure of up to $75 million across the remainder of 2026 and 2027.
That is a significant commitment to Ntorya at a point when the field is moving from infrastructure construction towards production and sustained development activity.
The figure also gives investors a much clearer indication of the scale of work now envisaged beyond first gas. The programme includes well intervention, testing, flowlines, gas processing equipment, drilling NT-3 and potentially further drilling at NT-E and NT-W, followed eventually by the obligatory CH-1 well.
The development programme is therefore no longer centred on one or two isolated operations. Ntorya is beginning to look like an active multi-well development campaign.
The clearest route to first production is now NT-2.
Aminex says removal of the bridge plugs and subsequent testing of NT-2 will begin in November 2026, followed by production into the Ntorya-Madimba pipeline in December.
The necessary flowlines will be constructed in parallel and completed before production begins, while the contract for the gas processing unit is expected to be signed later this month.
That provides a much more defined path to first revenue than investors previously had.
NT-2 does not now depend upon completion of NT-1 operations before Ntorya begins producing. Provided testing, flowlines, processing equipment and the pipeline are completed as scheduled, NT-2 can establish first production independently in December.
That distinction becomes particularly important because today's announcement introduces greater uncertainty around the timing of NT-1.
Wellhead maintenance and slickline operations on NT-1 remain scheduled to begin in October.
Those operations will determine whether a more substantial rig-operated workover is actually necessary.
This is new and useful detail. Rather than automatically proceeding directly into a full workover, APT will first assess the condition of the well using the October intervention programme.
If the initial work proves sufficient, the path towards production could be relatively straightforward.
If a rig-operated workover is required, however, Aminex says it will take place after drilling NT-3. In that circumstance, production from NT-1 would be delayed until December 2027.
That is clearly later than previously envisaged, but the important change in today's programme is that first gas no longer depends upon NT-1. NT-2 remains scheduled to begin production this December.
The revised structure therefore separates the immediate first-gas objective from the more extensive work that may ultimately be required to return NT-1 to production.
The newly prioritised Ntorya-Central location now has a formal well designation.
It will be drilled as NT-3.
Aminex says negotiations to contract the drilling rig are at a very advanced stage, with the contract expected to be signed in October 2026 and NT-3 scheduled to spud in December.
That is particularly relevant after months of investor interest in the availability and identity of the drilling rig. Aminex has still not named the rig or contractor, but today's announcement considerably narrows the uncertainty: commercial negotiations are advanced and a contract is expected within weeks.
If NT-3 is successful, Aminex says the well will be incorporated into the Ntorya development and first gas from NT-3 could be available in September 2027.
That immediately gives NT-3 a dual importance. It is both a well capable of providing additional reservoir information and, if successful, a development well with a defined route into production.
Perhaps the most interesting new information in today's RNS is the appearance of Ntorya-East and Ntorya-West.
Subject to the results from NT-3, the joint venture will have the option to drill up to two additional appraisal/development wells, NT-E and NT-W, on a back-to-back basis.
These would follow completion of NT-3 and, if required, the NT-1 workover.
This materially broadens the near-term drilling picture.
Only three weeks ago, attention was focused mainly on NT-Central and CH-1. Today's programme now raises the possibility of a sequence involving:
NT-3 → potentially NT-1 workover → NT-East → NT-West → CH-1
The precise order of NT-E and NT-W will depend upon the results of NT-3 and whether NT-1 requires rig intervention, but the direction is clear: APT is preparing options for a continuing drilling campaign rather than a single December well.
This also begins to show how the larger Field Development Plan may transition from a presentation of future locations into an actual sequence of development wells.
The introduction of NT-E and NT-W makes the December NT-3 well more strategically important than previously understood.
The RNS explicitly says the decision to drill those additional wells will depend upon the results from NT-3.
That suggests NT-3 is expected to provide information relevant to the positioning and justification of subsequent development activity across the field.
When APT first proposed bringing Ntorya-Central forward, Aminex explained that it had previously been planned as a later-stage development well and had been prioritised following APT's technical reappraisal of Ntorya.
Today's announcement begins to reveal what may follow that decision.
Rather than NT-Central simply replacing the timing of CH-1, it has now become the first well in what could develop into a sequence of additional Ntorya appraisal and development drilling.
CH-1 remains firmly within the programme.
Aminex describes it explicitly as an obligatory well under both the Development Licence and the Farmout Agreement, but says it will now be drilled at the end of the programme described in today's update.
That is a significant change in sequencing.
CH-1 was once expected to be the next major drilling event at Ntorya. The revised technical approach has progressively moved NT-Central ahead of it, and today's RNS potentially places NT-E, NT-W and an NT-1 workover ahead of CH-1 as well.
The important point is that CH-1 has not disappeared from the development. Its contractual status remains unchanged.
What has changed is the operator's preferred order of operations.
The emerging programme now appears designed to extract more information and potentially establish additional development wells across the existing Ntorya structure before moving on to the obligatory Chikumbi exploration target.
Today's announcement also gives investors their first meaningful view of what 2027 could look like operationally.
If NT-3 is successful, first gas from that well is targeted for September 2027.
If NT-1 requires a rig workover, its production would follow in December 2027.
Between and around those operations, the joint venture has the option to drill NT-E and NT-W back-to-back before eventually moving to CH-1.
Not all of those wells are guaranteed to be drilled during 2027, as the sequencing depends upon results as the programme progresses. Nevertheless, the approved provisional budget demonstrates that APT and Aminex are preparing financially for a considerably more active development programme than simply achieving first gas and stopping there.
The $75 million gross expenditure figure reinforces that point.
First gas is increasingly becoming the opening event in a much larger phase of Ntorya field development.
The Ntorya-Madimba pipeline also remains on schedule for completion in December.
TPDC has told Aminex that approximately 95% of pipelaying and infilling is now complete, while connection and metering work at the Madimba Gas Processing Plant is continuing.
That needs to be read alongside the recent China Petroleum Daily report stating that the 33.766 km pipeline achieved full-line connectivity on 14 September.
The two statements describe different measures of completion.
The Chinese contractor was reporting the physical connectivity of the pipeline itself. TPDC's percentage covers the wider pipelaying and infilling process while work continues on connections, metering and the remaining project infrastructure.
Together they indicate that the principal pipeline construction is very advanced, while final connection and commissioning-related activities continue towards December.
Today's RNS also identifies another procurement event worth watching.
Aminex expects the contract for the gas processing unit to be signed later this month.
The GPU will form part of the infrastructure needed to condition the initial Ntorya production before gas enters the wider system.
Combined with construction of the NT-2 flowlines and the continuing connection work at Madimba, its procurement provides another visible near-term milestone between today's announcement and December production.
This also gives investors a useful checklist for the coming weeks.
The GPU contract is expected before the end of September.
NT-1 wellhead and slickline operations begin in October.
The drilling-rig contract is expected in October.
NT-2 testing begins in November.
NT-3 is scheduled to spud in December.
NT-2 production and completion of the pipeline are targeted for December.
The operational pace is therefore about to increase markedly.
The announcement is particularly notable when compared with the position only two months ago.
In July, Aminex disclosed that APT had proposed material changes to the approved 2026 programme, including reduced expenditure and delays to first gas and CH-1. That disagreement ultimately led Aminex to issue a Notice of Dispute in August.
The 2 September announcement established a revised operational sequence following intervention and discussions involving the Tanzanian Government, TPDC, PURA, APT and Aminex.
Today's RNS takes that process another significant step forward.
The revised 2026 programme and provisional 2027 programme are now approved by the joint venture, backed by an expenditure plan of up to $75 million and supported by a defined sequence of operations extending well beyond first gas.
The focus has therefore moved decisively from disagreement over what should be done to execution of an agreed development programme.
There are several important messages in today's update.
The first is that December first gas remains intact, with NT-2 now providing the clearest route to initial production.
The second is that the joint venture has approved a substantial $75 million gross programme covering the remainder of 2026 and 2027, demonstrating a level of commitment extending far beyond the immediate first-gas milestone.
The third is that NT-Central has evolved into NT-3, with rig negotiations at a very advanced stage and first gas from a successful well targeted for September 2027.
Perhaps most importantly for the longer-term investment case, today's RNS introduces NT-East and NT-West as possible back-to-back appraisal/development wells following NT-3. That begins to reveal the next layer of the Ntorya development programme and shows how rapidly the field could progress once first production has been established.
There is greater uncertainty around NT-1, and CH-1 has moved further back in the drilling sequence. But neither prevents first production from progressing through NT-2, while the wider programme has actually expanded.
Three weeks ago, investors had a revised timetable.
Today they have something more substantial: an approved multi-well development programme, up to $75 million of planned expenditure, a December first-gas route, an imminent rig contract and the beginnings of a drilling sequence capable of carrying Ntorya deep into 2027.
Contributing Author: Andrew Eldridge
Aminex PLC, 23 September 2026, RNS 8676V, “Ntorya Operations Update”: approval of revised 2026 and provisional 2027 work programmes, up to $75 million gross expenditure, NT-2 December production, NT-1 programme, NT-3 drilling, NT-E/NT-W options, CH-1 sequencing and pipeline progress.
Aminex PLC, 2 September 2026, “Ntorya – Revised Implementation Programme Agreed”: revised operational sequence agreed following the 26 August Tanzanian Government meeting, including NT-1, NT-2, NT-Central and December first gas.
Aminex PLC, 14 July 2026, “Ruvuma Operations and Corporate Update”: APT's proposed amendments to the original 2026 work programme and the resulting disagreement over first gas and CH-1.
Aminex PLC, Annual Report and Accounts 2025: Ntorya phased Field Development Plan and longer-term production profile.
China Petroleum Daily / CNPC, 17 September 2026: contractor report confirming full-line connectivity of the 33.766 km Ntorya-Madimba pipeline on 14 September.